Gregory CheradamePortfolio

SAP rollout to Nutriad US plants

Adisseo / Nutriad · SAP Logistics Functional Consultant and Trainer

Rolled Adisseo's group SAP solution out to Nutriad, a company it had acquired, across several US sites: logistics design workshops, master-data conversion, purchasing, sales, inventory and production flows, testing and user training.

Client / organization
Adisseo / Nutriad
Consulting firm
VISEO USA
Role
SAP Logistics Functional Consultant and Trainer
Period
Jan 2019 - May 2019
Location
Hampshire, Illinois, USA

Business context

Adisseo, a world leader in animal nutrition additives, had acquired Nutriad and was rolling its group SAP solution out to Nutriad's US plants and warehouses. The logistics processes (sales, purchasing, inventory and production) had to be designed for the new sites, Nutriad's master data converted and loaded, and users trained to work in SAP.

Key contributions

  • Led the SAP logistics design workshops and the functional analysis and design for the new sites.
  • Converted and uploaded Nutriad's master data.
  • Designed and tested stock transfer orders, intercompany replenishment, stock adjustments, sales orders, production planning, production orders and confirmations.
  • Ran change management, delivered user training and wrote the user guides.

Responsibilities in detail

Analysis & design

  • Requirements and design workshops
  • Business requirements analysis
  • Functional analysis and design

Process scope

  • Stock transfer orders
  • Intercompany replenishment orders
  • Stock adjustments
  • Production planning
  • Production orders and confirmations
  • Sales orders

Data

  • Master data conversion and upload

Testing

  • Unit tests
  • Acceptance tests on purchasing, sales, inventory and production flows

Support & training

  • Change management
  • User training
  • User guides

Process scope

Area Flows I designed and tested
Purchasing and inventory (MM/WM) Stock transfer orders, intercompany replenishment orders, stock adjustments
Production (PP) Production planning, production orders and confirmations
Sales (SD) Sales orders
Data Conversion and upload of Nutriad master data

How I worked

I led the logistics design workshops with Nutriad's users, then wrote the functional analysis and design for each flow. I converted and uploaded the master data, ran the unit tests and organized the acceptance tests on the purchasing, sales, inventory and production flows. As trainer on the project, I also ran change management, delivered the user training and wrote the user guides.

Technology landscape